Applied Digital

Applied Digital designs, builds and operates data centers for AI and high-performance computing. Its Polaris Forge 1 deliveries supply the physical infrastructure behind CoreWeave’s contracted deployments.

kindCompany
founded2021
Event history

Delivering the building and its power

Applied Digital develops data centers and colocation infrastructure for AI, cloud and other computing workloads. The company dates its business to 2021. Its Polaris Forge model provides the facility, power distribution and cooling for customers' computing equipment. [1]

On October 27, 2025, Applied Digital reported the first 50 MW ready for service in the first 100 MW building at Polaris Forge 1. CoreWeave was the tenant. The initial delivery was part of a 400 MW leased program, rather than evidence that the entire contracted campus was already operating. [1][2]

The company's October 2026 earnings release identified a later stage: another 75 MW phase reached ready-for-service on October 1, bringing operational critical IT load at Polaris Forge 1 to 250 MW across two buildings. The dated delivery measure remains distinct from possible future power capacity and the campus's ultimate design. [3]

Sources

  1. Applied Digital Achieves Ready for Service for Phase 1 at Polaris Forge 1 Building 1 for CoreWeave

    Applied Digital · Oct 27, 2025

  2. First 50MW ready for service at Applied Digital data center in Ellendale, North Dakota

    Data Center Dynamics · Oct 27, 2025

  3. Applied Digital Reports Fiscal First Quarter 2027 Results

    Applied Digital · Oct 7, 2026